Public Works Active Projects

Burlington -River Water Main Improvement Project

The project includes the rehabilitation of sections of water main on River Drive (from Ogden Avenue to the dead end north of Lacey Avenue) and Burlington Avenue (between Dumoulin Avenue and Lincoln Avenue). Rehabilitation of these water mains have been prioritized to improve reliability, reduce the frequency of main breaks, and to align with the upcoming 2021 Road Resurfacing Program. Water main rehabilitation is an ongoing initiative and furthers the strategic priority of delivering high quality Village services and dependable infrastructure.

Project Engineer: Baxter & Woodman Associates
Project Contractor:
 Austin Tyler Construction
Project Commencement: In progress.
Project Conclusion: June 2021
Residents Impact: Temporary sidewalk closure and temporary lane closures. Temporary water shut-offs to adjoining businesses. Notification will be provided in advance of shut-offs.
Project Update - May 7, 2021: Work continues with the Village's contractor, Austin-Tyler, with restoration for the entirety of the project. Concrete and pavement patching have been completed, and landscape restoration is under way. 

Indiana-Wellington Water Main Improvement Project

The project includes the rehabilitation of sections of water main on Indiana Ave. (between Molex Dr. and Ogden Ave.), and Wellington Ave. (from Indiana Ave. to the end section). Water main rehabilitation is an ongoing initiative of the Public Works Department’s infrastructure improvement program and furthers the strategic priority of delivering high quality Village services and dependable infrastructure. Water mains are replaced and upgraded to improve reliability, pressure and fire flow.

Project Contractor: Strand Associates
Project Contractor:
 
J. Congdon Sewer Service
Project Commencement: In progress.
Project Conclusion: June 2021
Residents Impact: Temporary sidewalk closure and temporary lane closures. Temporary water shut-offs to adjoining businesses. Notification will be provided in advance of shut-offs.
Project Update - May 7, 2021: Work continued this week with the Village's contractor, J. Congdon Sewer, completing the water main lining portion under Ogden Avenue. The water main was pressure tested and chlorinated. Restoration on the project will begin next week.

2021 Annual Road Program

The scope of the proposed improvements will include grinding & resurfacing, concrete curb repair and some ancillary curb and sidewalk removal & replacement at intersection sidewalk crossings to comply with ADA requirements. The work includes roadway improvements on a total 20 Village streets.

Project Consultant:  Engineering Enterprises
Project Contractor: K-Five Construction Company
Project Commencement: May 10, 2021.
Project Conclusion: Fall 2021.
Residents Impact: Temporary sidewalk closure and temporary lane closures.
Project Update - May 7, 2021: Project layout will begin next week. 
Rehabilitation Map: Access the 2021 Street Rehabilitation Map (PDF) to learn more.

Abbeywood and Green Trails Resurfacing Improvement

The scope of the proposed improvements will include grinding & resurfacing, concrete curb repair and some ancillary curb and sidewalk removal & replacement at intersection sidewalk crossings to comply with ADA requirements. 

Project Consultant:  Thomas Engineering
Project Contractor: K-Five Construction Company
Project Commencement: June 1, 2021.
Project Conclusion: Fall 2021.
Residents Impact: Temporary sidewalk closure and temporary lane closures.
Project Update - May 7, 2021: Return for project updates once project commences. 

Road CIP. JPG

Contact Us

  1. Adam Hall


    Assistant Public Works Director
    Email

    Administration & Engineering
    4907 Yackley Ave.
    Lisle, IL 60532
    Directions
    Email

    Ph: 630-271-4170
    Fax: 630-271-4160

    Hours


    Hours
    Monday - Friday
    7 a.m. - 3:30 p.m.

    Staff Directory